CareerExamPro

NCMA Certified Professional Contract Manager (CPCM) practice test

27 practice questions for this exam, each with a full explanation and cited rule or blueprint reference.

Start practising

NCMA CFCM (FAR), CSCP, CPIM & CPSM: practice drill

10 realistic exam questions, graded as you go, with the exact rule or statute citation for every answer. Start free, no sign-up.

Timed mock exam

27 questions in 32 minutes, drawn from every topic. No answers shown until the end, then a full score breakdown, your weakest topics and a review of what you missed.

Practice tests that prepare you for this exam

Practise by topic

About this exam

Agency / Issuer
NCMA
Region
United States

Exact question counts, passing scores, and allowed reference materials vary by testing window and state/agency. Always confirm current rules with the official testing provider.

Sample questions

A medical-equipment manufacturer buys a specialized $12 proprietary sensor representing less than 0.5% of total spend, yet it is sole-sourced from one overseas foundry and a shortage would halt the entire assembly line. In the Kraljic Purchasing Portfolio Matrix, how is this item classified and what is the primary sourcing strategy?

  1. Leverage item (high profit impact, low supply risk); aggressively consolidate volumes and run competitive reverse auctions to cut unit price.
  2. Non-Critical/Routine item (low profit impact, low supply risk); automate ordering through purchasing cards and electronic catalogs.
  3. Strategic item (high profit impact, high supply risk); form a joint-venture equity alliance focused primarily on shared cost engineering.
  4. Bottleneck item (low profit impact, high supply risk); prioritize supply continuity through safety stock, long-term supply agreements, and qualifying backup sources.
Show the answer

D. Bottleneck item (low profit impact, high supply risk); prioritize supply continuity through safety stock, long-term supply agreements, and qualifying backup sources.

In Peter Kraljic's Purchasing Portfolio Matrix (Profit Impact × Supply Risk), a low-spend component with severe supply vulnerability (sole source, line-stoppage risk) is a Bottleneck item. Unlike Leverage items (price/volume competition) or Non-Critical items (process automation), the primary procurement objective for Bottleneck items is ensuring continuity of supply—via buffer inventory, vendor-held stock, long-term contracts, and actively qualifying alternate sources or redesigning out the single point of failure.

Reference: ISM CPSM & ASCM CSCP — Kraljic Purchasing Portfolio Matrix (Bottleneck Items)

A program manager without a contracting warrant verbally instructs a vendor to deliver $38,000 in urgent lab supplies, which the agency receives and uses. Under FAR Part 1, what is the status of this agreement and who holds authority to ratify it?

  1. It is a binding implied-in-fact contract that the Contracting Officer may retroactively fund through an administrative modification.
  2. An unauthorized commitment ratifiable only by the Head of the Contracting Activity (or delegate no lower than Chief of the Contracting Office).
  3. It is an informal constructive change that the Contracting Officer's Representative must document and convert into a bilateral supplemental agreement.
  4. It is a valid simplified acquisition under the micro-purchase exception that any warranted Contract Specialist may approve once funds are certified.
Show the answer

B. An unauthorized commitment ratifiable only by the Head of the Contracting Activity (or delegate no lower than Chief of the Contracting Office).

Under FAR 1.602-1, only warranted Contracting Officers may bind the Government. An agreement made by an unauthorized official is an unauthorized commitment under FAR 1.602-3, which may be ratified only by the Head of the Contracting Activity (HCA) unless delegated no lower than the Chief of the Contracting Office, provided all seven FAR 1.602-3(c) conditions are satisfied.

Reference: FAR 1.602-1 & FAR 1.602-3 — Contracting Officer Authority and Ratification of Unauthorized Commitments

Making a machined housing in-house requires $240,000 in annual fixed costs and $18/unit variable cost. Outsourcing to a supplier requires $30,000 in annual tooling/administration fixed costs and a $30/unit purchase price. What is the breakeven annual volume, and which option is cheaper at 20,000 units/year?

  1. Breakeven is 20,000 units; both options cost exactly $600,000 per year at that volume.
  2. Breakeven is 17,500 units; at 20,000 units, making in-house is cheaper by $30,000 per year ($600,000 vs. $630,000).
  3. Breakeven is 17,500 units; at 20,000 units, buying from the supplier is cheaper by $30,000 per year.
  4. Breakeven is 22,500 units; at 20,000 units, buying from the supplier saves $30,000 in fixed overhead.
Show the answer

B. Breakeven is 17,500 units; at 20,000 units, making in-house is cheaper by $30,000 per year ($600,000 vs. $630,000).

Set total costs equal to find the make-vs-buy indifference point: Q* = (FC_make - FC_buy) / (VC_buy - VC_make) = ($240,000 - $30,000) / ($30 - $18) = $210,000 / $12 = 17,500 units. Because in-house manufacturing has the lower variable cost ($18 vs. $30), making is cheaper above 17,500 units. At 20,000 units, Make = $240,000 + (20,000 × $18) = $600,000, while Buy = $30,000 + (20,000 × $30) = $630,000, saving $30,000/year.

Reference: ISM CPSM, ASCM CPIM & NCMA CMBOK — Make-vs-Buy Breakeven Analysis

Taking this exam soon?

Tell us which exam domains or calculation drills you want more practice on.

Other GovCon (FAR) & Supply Chain exams